Application


Building

Windows reconstructed or replaced by new ones. Retrofitting of roofs completed. Sunspaces erected to receive P.V. solar panels and provide daylighting and natural ventilation.(April 2007)

Following grindblasting and scraping of external building surfaces, reconstruction of the building shell completed, including structural reinforcement of external walls where needed. External insulation and replastering of walls is completed. Work on façade reconstruction of neo-classical decorative elements is completed. Final replastering of façade to be completed next week.
The reconstruction and insulation of all parts of the roof was completed at the end of February 2007. Windows reconstruction including low-e double glazing and night insulation is completed. New windows will be installed to replace old ones as soon as external “gros-oeuvre” work is completed, so that the whole building is tightly sealed. Remodelling of the interior includes construction of verandas as extension of reading rooms. (March 2007)

The project is in construction phase, due to be completed by the end of April, 2007. Monitoring is scheduled to last for one year starting May 2007.
External insulation and replastering of walls and reconstruction and insulation of all parts of the roof is also underway.
Windows reconstruction including low-e double glazing and night insulation will be installed to replace old ones as soon as external “gros-oeuvre” work is completed, so that the whole building is tightly sealed by the end of February 2007. (January 2007)

Plants

Daylighting/natural ventilation ducts constructed. New electrical installation underway. (April 2007)
Shading, day lighting, and natural ventilation systems will be integrated to the building structure in the beginning of March 2007.

All other systems to be integrated to the building (pv cells, solar collectors, shading systems) as well as electrical and mechanical systems and BEMS are already purchased by our sponsors following market research by our team, in order to select the systems best suited to the building.



BEMS

No Information available.





 

Put your mouse over the picture to see them in full size.