Application
Building
The construction phase was managed within the foreseen time schedule.
Problems related to building:
Concerning acoustics additional absorbants on walls in the workshop are needed.
There have been problems with moisture from rain and snow entering the system from the air inlet tower in base A. some fungosity has been observed.
Plants
Complete and running.
Prototype hinges and sealing profiles for ACC windows were made. Production of prototype test versions of ACC windows and solar collector has been delayed.
Preparation for production of prototype ACC windows and solar collector is ongoing (September 06).
BEMS
The BEMS is in operatoin.