Commissioning

Commissioning of turbines completed with final faults resolved May 2007.

Complete although inverter repair outstanding.
First service took place in January 2007. One inverter defective. Logging system fitted. Additional power meter fitted. New turbine blades fitted.(March 2007)

Target provided with design of Wind Turbines 33800 kwh actual output for first year of operation 5750 kwh.
First service outstanding but no fault in the installation has been identified.
Detailed discussions took place with Installer. The poor output relates to local wind conditions causing gusting rather than a clean air flow and there has been unusual weather. (December 2006)

Wind turbines not properly commissioned. Antivibration brakes yet to be fitted. Poor performance of wind turbines continuing. Great difficulties in getting installers to visit site to investigate. (March 2006)

Power output of turbines well below target. Slow progress with turbine installers to investigate poor electricity generation (December 2005)





 